CENSE Book a free facility review
All projects

Phased HVAC renewal in a production-building basement

  • HVAC systems
  • Black utilities & energy
  • Electrical & instrumentation
  • CAD, 3D & BIM
  • 3D clash detection
  • FAT / SAT
  • Commissioning
  • Handover to system owner
3D coordination model of the basement: air ducts, piping, cable trays and valves stacked in one corridor
The 3D coordination model: HVAC ducts, utility piping and cable trays in one shared corridor, checked for clashes.

The challenge

The HVAC installations in the basement of a production building are being renewed. The work runs in phases, with each demolition and rebuild step in a fixed order.

What we do

  • Project management: planning, cost follow-up, site meetings and alignment with operations, safety and the user.
  • 3D coordination of HVAC, civil works and sprinklers with clash detection, with every demolition and rebuild step modelled.
  • Engineering support: technical data sheets, calculations and construction drawings.
  • Site follow-up for HVAC, black utilities, electricity and automation, including factory and site acceptance tests.
  • Commissioning, as-built checks and the handover steps to the system owner.

Execution timeline

  1. PreparationJul 2026
  2. Phased constructionfrom Aug 2026
  3. Handover and close-outto Nov 2027

Where it stands

The project is in execution. One CENSE team covers project management, both engineering disciplines and CAD, so a question from site goes straight to the engineer who can answer it.

Next projectCleanroom requirements aligned across the US, EU and China